Westhaven Seawall Upgrade progress update
The upgrade to the seawall along Westhaven's northern reclamation began in early March under the guidance of Eke Panuku. This project aims to address the challenges posed by adverse weather events and king tides, which have led to significant inundation in the area.
Current construction status:
In April, John Fillmore Contracting (JFC) initiated underground utilities ducting and drainage works in the area. Progress is being made in phases, with completion expected for this portion of the project by the end of May.
Following the utilities upgrades, JFC will shift focus to the seawall reconstruction. This involves demolishing footpaths, installing stormwater outfalls, constructing a new precast wall, establishing raingardens and reconstructing footpaths.
The planned relocation of three pÅhutukawa trees is scheduled to take place shortly. To ensure safety, the site area will be temporarily expanded for approximately one week while this takes place.
Traffic management:
Temporary traffic management measures, including a 10km/h speed limit, have been implemented to ensure the safety of work crews, pedestrians and motorists.
Westhaven Drive has been reduced to a single lane, with two-way traffic being regulated by a traffic light system. Given the complexity of traffic flow, ongoing adjustments are being made to optimise traffic flow prioritisation. Please be aware that the traffic lights operate on sensors, requiring vehicles to stop within close proximity for detection.
We appreciate your patience during these improvement efforts.
Fire alarm system upgrade
You might have noticed contractors installing cables along certain piers to accommodate an upgrade to our fire alarm system, which includes all call points and sirens. This effort is in response to the fire alarm system on our piers reaching the end of its operational life, necessitating replacement.
The traditional tower-style call points will be replaced with modern stainless steel pedestals. The upgraded system will feature one to two speakers per pier, capable of broadcasting fire alarm alerts, as well as voice messages.
The replacement is progressing pier by pier, and contractors have made good progress, completing cabling installation along all the piers. The cables across these piers are now being connected to cabinets.
Following the completion of the cable installation, all technical and system connections to fire panels will be carried out and commissioned. The project is scheduled for completion by mid-June 2024.
The contractors are doing their best to minimise disruption for pier users during the upgrade process.
We appreciate your patience and understanding as this project progresses.
Maintenance
In addition to our regular maintenance schedule, the following tasks have recently been completed or are currently underway: